Swansea Bay Tidal Lagoon loses legal battleGeo ConDec 22, 20221 min readThe developer of the £1.3bn Swansea Bay Tidal Lagoon has lost its appeal against a court ruling that said it failed to commence work on the project within the relevant five year timeframe. Click here for full articleSource & Image - Ground Engineering
The developer of the £1.3bn Swansea Bay Tidal Lagoon has lost its appeal against a court ruling that said it failed to commence work on the project within the relevant five year timeframe. Click here for full articleSource & Image - Ground Engineering